ID |
Task Name |
Duration |
Start |
Finish |
Resource Names |
% Complete |
1 |
Basic Training |
5 days |
Fri 7/29/05 |
Fri 8/5/05 |
John A. Martin,Shawn Brinkman,Bonnie Wright,Steve
Jilek |
0% |
2 |
Phase I - Design |
5 days |
Mon 8/8/05 |
Fri 8/12/05 |
|
0% |
3 |
Prepare Preliminary Architecture
Document |
5 days |
Mon 8/8/05 |
Fri 8/12/05 |
|
0% |
4 |
Implementation Architecture Design
& Document |
24 hrs |
Mon 8/8/05 |
Wed 8/10/05 |
|
0% |
5 |
Agree on Final Lab Design |
1 day |
Fri 8/12/05 |
Fri 8/12/05 |
|
0% |
6 |
Phase II - Test Lab |
11 days |
Mon 8/15/05 |
Mon 8/29/05 |
|
0% |
7 |
Set Up Lab Warehouse |
1 day |
Mon 8/15/05 |
Mon 8/15/05 |
|
0% |
8 |
Load MGSFT Administrator
Software |
2 hrs |
Mon 8/15/05 |
Mon 8/15/05 |
|
0% |
9 |
Create Policies |
2 hrs |
Mon 8/15/05 |
Mon 8/15/05 |
|
0% |
10 |
Create Shedules |
2 hrs |
Mon 8/15/05 |
Mon 8/15/05 |
|
0% |
11 |
Certify Warehouse for
Operations |
2 hrs |
Mon 8/15/05 |
Mon 8/15/05 |
|
0% |
12 |
Setup Lab Distribution Servers and
Deployment Locations |
2 days |
Tue 8/16/05 |
Wed 8/17/05 |
|
0% |
13 |
Define Distribution Servers |
2 hrs |
Tue 8/16/05 |
Tue 8/16/05 |
|
0% |
14 |
Define Distribution
Locations |
2 hrs |
Tue 8/16/05 |
Tue 8/16/05 |
|
0% |
15 |
Install Distrbution Server on
Servers |
4 hrs |
Tue 8/16/05 |
Tue 8/16/05 |
|
0% |
16 |
Test Warehouse and Deployment
Locations |
4 hrs |
Wed 8/17/05 |
Wed 8/17/05 |
|
0% |
17 |
Certify Distribution
Heirarchy |
4 hrs |
Wed 8/17/05 |
Wed 8/17/05 |
|
0% |
18 |
Setup and Test SPM |
0.5 days |
Thu 8/18/05 |
Thu 8/18/05 |
|
0% |
19 |
Install and Configure SPM |
4 hrs |
Thu 8/18/05 |
Thu 8/18/05 |
|
0% |
20 |
Package Preperation |
11 days |
Mon 8/15/05 |
Mon 8/29/05 |
|
0% |
21 |
Plan and Design Package
Standards |
3 days |
Mon 8/15/05 |
Wed 8/17/05 |
|
0% |
22 |
Agree on Package Standards |
1 day |
Thu 8/18/05 |
Thu 8/18/05 |
|
0% |
23 |
Packaging |
7 days |
Fri 8/19/05 |
Mon 8/29/05 |
|
0% |
24 |
Create |
3 days |
Fri 8/19/05 |
Tue 8/23/05 |
|
0% |
25 |
Create Packages |
3 days |
Fri 8/19/05 |
Tue 8/23/05 |
|
0% |
26 |
Test |
2 days |
Wed 8/24/05 |
Thu 8/25/05 |
|
0% |
27 |
Test packages |
2 days |
Wed 8/24/05 |
Thu 8/25/05 |
|
0% |
28 |
Certify |
2 days |
Fri 8/26/05 |
Mon 8/29/05 |
|
0% |
29 |
Delivery of Packages |
1 day |
Fri 8/26/05 |
Fri 8/26/05 |
|
0% |
30 |
Integration with Software
GPOs |
1 day |
Mon 8/29/05 |
Mon 8/29/05 |
|
0% |
31 |
Phase III Beta testing |
7 days |
Tue 8/30/05 |
Wed 9/7/05 |
|
0% |
32 |
Set up & test Clients |
3 days |
Tue 8/30/05 |
Thu 9/1/05 |
|
0% |
33 |
Set up & test policies |
1 day |
Fri 9/2/05 |
Fri 9/2/05 |
|
0% |
34 |
Add Client Machines to Active
Directory with Object Units |
4 hrs |
Mon 9/5/05 |
Mon 9/5/05 |
|
0% |
35 |
Associate Group Policies with Active
Directory Object Units |
1 day |
Mon 9/5/05 |
Tue 9/6/05 |
|
0% |
36 |
Create Schedules and Attach
Schedules |
1.5 days |
Tue 9/6/05 |
Wed 9/7/05 |
|
0% |
37 |
Install Managed Device |
4 hrs |
Tue 9/6/05 |
Tue 9/6/05 |
|
0% |
38 |
Full Client Setup &
Testing |
1 day |
Wed 9/7/05 |
Wed 9/7/05 |
|
0% |
39 |
Phase IV Proof of Concept
Pilot |
17 days |
Thu 9/8/05 |
Fri 9/30/05 |
|
0% |
40 |
Setup Production
Warehouse |
7 days |
Thu 9/8/05 |
Fri 9/16/05 |
|
0% |
41 |
Load Warehouse |
2 days |
Thu 9/8/05 |
Fri 9/9/05 |
|
0% |
42 |
Create Policies |
2 days |
Mon 9/12/05 |
Tue 9/13/05 |
|
0% |
43 |
Create Schedules |
2 days |
Wed 9/14/05 |
Thu 9/15/05 |
|
0% |
44 |
Certify Warehouse for
Operations |
1 day |
Fri 9/16/05 |
Fri 9/16/05 |
|
0% |
45 |
Define Initial Distribution
Heirchy |
4 days |
Mon 9/19/05 |
Thu 9/22/05 |
|
0% |
46 |
Define Initial Distribution
Locations |
1 day |
Mon 9/19/05 |
Mon 9/19/05 |
|
0% |
47 |
Define Reporting Location |
1 day |
Tue 9/20/05 |
Tue 9/20/05 |
|
0% |
48 |
Test Warehouse and Distribution
Locations |
1 day |
Wed 9/21/05 |
Wed 9/21/05 |
|
0% |
49 |
Certify Warehouses |
1 day |
Thu 9/22/05 |
Thu 9/22/05 |
|
0% |
50 |
Set-up Client Adoption
Process |
5 days |
Fri 9/23/05 |
Thu 9/29/05 |
|
0% |
51 |
Design Client Bootstrap |
1 day |
Fri 9/23/05 |
Fri 9/23/05 |
|
0% |
52 |
Create MGSFT setup.ini File |
1 day |
Mon 9/26/05 |
Mon 9/26/05 |
|
0% |
53 |
Verify Client Bootstrap |
1 day |
Tue 9/27/05 |
Tue 9/27/05 |
|
0% |
54 |
Install Client |
1 day |
Wed 9/28/05 |
Wed 9/28/05 |
|
0% |
55 |
Test Install |
1 day |
Thu 9/29/05 |
Thu 9/29/05 |
|
0% |
56 |
Agree on Final Production
Design |
1 day |
Fri 9/30/05 |
Fri 9/30/05 |
|
0% |
57 |
Wrap-Up Summit |
1 day |
Fri 9/30/05 |
Fri 9/30/05 |
|
0% |
58 |
Phase V Client Distribution to
PBCSD |
158 days |
Mon 10/3/05 |
Wed 5/10/06 |
|
0% |
59 |
Client Rollout to Strategic
Servers |
3 days |
Mon 10/3/05 |
Wed 10/5/05 |
|
0% |
60 |
Desktop Rollout Deployment to North
Central Area by Ascending School Number |
31 days |
Thu 10/6/05 |
Thu 11/17/05 |
|
0% |
61 |
Desktop Rollout Deployment to South
Central Area by Ascending School Number |
31 days |
Fri 11/18/05 |
Fri 12/30/05 |
|
0% |
62 |
Desktop Rollout Deployment to West
Area by Ascending School Number |
31 days |
Mon 1/2/06 |
Mon 2/13/06 |
|
0% |
63 |
Desktop Rollout Deployment to South
Area by Ascending School Number |
31 days |
Tue 2/14/06 |
Tue 3/28/06 |
|
0% |
64 |
Desktop Rollout Deployment to North
Area by Ascending School Number |
31 days |
Wed 3/29/06 |
Wed 5/10/06 |
|
0% |