ManageSoft June 2005





Project Start:
Project Finish:
Fri 7/18/05
Wed 5/10/06


Tasks


ID
Task Name
Duration Start Finish Resource Names % Complete
1
Basic Training
5 days Fri 7/29/05 Fri 8/5/05 John A. Martin,Shawn Brinkman,Bonnie Wright,Steve Jilek 0%
2
Phase I - Design
5 days Mon 8/8/05 Fri 8/12/05   0%
3
Prepare Preliminary Architecture Document
5 days Mon 8/8/05 Fri 8/12/05   0%
4
Implementation Architecture Design & Document
24 hrs Mon 8/8/05 Wed 8/10/05   0%
5
Agree on Final Lab Design
1 day Fri 8/12/05 Fri 8/12/05   0%
6
Phase II - Test Lab
11 days Mon 8/15/05 Mon 8/29/05   0%
7
Set Up Lab Warehouse
1 day Mon 8/15/05 Mon 8/15/05   0%
8
Load MGSFT Administrator Software
2 hrs Mon 8/15/05 Mon 8/15/05   0%
9
Create Policies
2 hrs Mon 8/15/05 Mon 8/15/05   0%
10
Create Shedules
2 hrs Mon 8/15/05 Mon 8/15/05   0%
11
Certify Warehouse for Operations
2 hrs Mon 8/15/05 Mon 8/15/05   0%
12
Setup Lab Distribution Servers and Deployment Locations
2 days Tue 8/16/05 Wed 8/17/05   0%
13
Define Distribution Servers
2 hrs Tue 8/16/05 Tue 8/16/05   0%
14
Define Distribution Locations
2 hrs Tue 8/16/05 Tue 8/16/05   0%
15
Install Distrbution Server on Servers
4 hrs Tue 8/16/05 Tue 8/16/05   0%
16
Test Warehouse and Deployment Locations
4 hrs Wed 8/17/05 Wed 8/17/05   0%
17
Certify Distribution Heirarchy
4 hrs Wed 8/17/05 Wed 8/17/05   0%
18
Setup and Test SPM
0.5 days Thu 8/18/05 Thu 8/18/05   0%
19
Install and Configure SPM
4 hrs Thu 8/18/05 Thu 8/18/05   0%
20
Package Preperation
11 days Mon 8/15/05 Mon 8/29/05   0%
21
Plan and Design Package Standards
3 days Mon 8/15/05 Wed 8/17/05   0%
22
Agree on Package Standards
1 day Thu 8/18/05 Thu 8/18/05   0%
23
Packaging
7 days Fri 8/19/05 Mon 8/29/05   0%
24
Create
3 days Fri 8/19/05 Tue 8/23/05   0%
25
Create Packages
3 days Fri 8/19/05 Tue 8/23/05   0%
26
Test
2 days Wed 8/24/05 Thu 8/25/05   0%
27
Test packages
2 days Wed 8/24/05 Thu 8/25/05   0%
28
Certify
2 days Fri 8/26/05 Mon 8/29/05   0%
29
Delivery of Packages
1 day Fri 8/26/05 Fri 8/26/05   0%
30
Integration with Software GPOs
1 day Mon 8/29/05 Mon 8/29/05   0%
31
Phase III Beta testing
7 days Tue 8/30/05 Wed 9/7/05   0%
32
Set up & test Clients
3 days Tue 8/30/05 Thu 9/1/05   0%
33
Set up & test policies
1 day Fri 9/2/05 Fri 9/2/05   0%
34
Add Client Machines to Active Directory with Object Units
4 hrs Mon 9/5/05 Mon 9/5/05   0%
35
Associate Group Policies with Active Directory Object Units
1 day Mon 9/5/05 Tue 9/6/05   0%
36
Create Schedules and Attach Schedules
1.5 days Tue 9/6/05 Wed 9/7/05   0%
37
Install Managed Device
4 hrs Tue 9/6/05 Tue 9/6/05   0%
38
Full Client Setup & Testing
1 day Wed 9/7/05 Wed 9/7/05   0%
39
Phase IV Proof of Concept Pilot
17 days Thu 9/8/05 Fri 9/30/05   0%
40
Setup Production Warehouse
7 days Thu 9/8/05 Fri 9/16/05   0%
41
Load Warehouse
2 days Thu 9/8/05 Fri 9/9/05   0%
42
Create Policies
2 days Mon 9/12/05 Tue 9/13/05   0%
43
Create Schedules
2 days Wed 9/14/05 Thu 9/15/05   0%
44
Certify Warehouse for Operations
1 day Fri 9/16/05 Fri 9/16/05   0%
45
Define Initial Distribution Heirchy
4 days Mon 9/19/05 Thu 9/22/05   0%
46
Define Initial Distribution Locations
1 day Mon 9/19/05 Mon 9/19/05   0%
47
Define Reporting Location
1 day Tue 9/20/05 Tue 9/20/05   0%
48
Test Warehouse and Distribution Locations
1 day Wed 9/21/05 Wed 9/21/05   0%
49
Certify Warehouses
1 day Thu 9/22/05 Thu 9/22/05   0%
50
Set-up Client Adoption Process
5 days Fri 9/23/05 Thu 9/29/05   0%
51
Design Client Bootstrap
1 day Fri 9/23/05 Fri 9/23/05   0%
52
Create MGSFT setup.ini File
1 day Mon 9/26/05 Mon 9/26/05   0%
53
Verify Client Bootstrap
1 day Tue 9/27/05 Tue 9/27/05   0%
54
Install Client
1 day Wed 9/28/05 Wed 9/28/05   0%
55
Test Install
1 day Thu 9/29/05 Thu 9/29/05   0%
56
Agree on Final Production Design
1 day Fri 9/30/05 Fri 9/30/05   0%
57
Wrap-Up Summit
1 day Fri 9/30/05 Fri 9/30/05   0%
58
Phase V Client Distribution to PBCSD
158 days Mon 10/3/05 Wed 5/10/06   0%
59
Client Rollout to Strategic Servers
3 days Mon 10/3/05 Wed 10/5/05   0%
60
Desktop Rollout Deployment to North Central Area by Ascending School Number
31 days Thu 10/6/05 Thu 11/17/05   0%
61
Desktop Rollout Deployment to South Central Area by Ascending School Number
31 days Fri 11/18/05 Fri 12/30/05   0%
62
Desktop Rollout Deployment to West Area by Ascending School Number
31 days Mon 1/2/06 Mon 2/13/06   0%
63
Desktop Rollout Deployment to South Area by Ascending School Number
31 days Tue 2/14/06 Tue 3/28/06   0%
64
Desktop Rollout Deployment to North Area by Ascending School Number
31 days Wed 3/29/06 Wed 5/10/06   0%

Resources


ID Name Group Max Units Peak Units
1 MGSFT Prj Mgr   100% 0%
2 MGSFT SrConsultant   100% 0%
3 MGSFT Consultant   100% 0%
4 MGSFT Trainer   100% 0%
5 MGSFT Sr Mgt   100% 0%
6 Eng   100% 0%
7 Sr Mgt   100% 0%
8 PrjMgr   100% 0%
9 Engineer1   100% 0%
10 Engineer2   100% 0%
11 John A. Martin   100% 100%
12 Shawn Brinkman   100% 100%
13 Bonnie Wright   100% 100%
14 Steve Jilek   100% 100%

Assignments


Task ID Task Name Resource Name Work Start Finish % Work Complete
1 Basic Training John A. Martin 48 hrs Fri 7/29/05 Fri 8/5/05 0%
1 Basic Training Shawn Brinkman 48 hrs Fri 7/29/05 Fri 8/5/05 0%
1 Basic Training Bonnie Wright 48 hrs Fri 7/29/05 Fri 8/5/05 0%
1 Basic Training Steve Jilek 48 hrs Fri 7/29/05 Fri 8/5/05 0%


Microsoft Home Page
Microsoft Project Home Page